Article 13 - INSPECTION

Section 27-719

Section 27-719

  §  27-719  General.  The  applicable  provisions  of  article seven of
subchapter one of this chapter shall apply.

Section 27-720

Section 27-720

  §  27-720  Boring  and  test  pit  operations.  Boring  and  test  pit
operations shall be subject to controlled inspection, except that  fifty
per  cent or less of the required number of borings and/or test pits may
be inspected by an architect or engineer other  than  the  architect  or
engineer  designated  for  controlled inspection. The records of borings
and/or test pits shall be attested to as follows:
  (a) The architect or  engineer  shall  file  a  report  stating  which
borings  and/or test pits were performed under his or her inspection and
whether such inspection was performed personally or  otherwise.  If  the
inspection  was  not  made  personally by the architect or engineer, the
name and address of the inspector shall be noted. It  shall  be  stated:
that  the  borings  and/or  test  pits  so  inspected were made and were
carried to the depths indicated; that, to the best of the architect's or
engineer's knowledge and belief, the description and  classification  of
the  soils  are  a  true  description  of the samples recovered from the
respective borings and/or test pits; that such samples were recovered at
the  levels  indicated;  and  that  the  boring  and/or  test  pit  work
progressed  in  such  manner  that  the samples recovered are reasonably
representative of the subsurface conditions.
  (b) The accuracy of the other data indicated  on  the  boring  records
shall be attested to by the drilling contractor or by the driller making
the borings.

Section 27-721

Section 27-721

  §  27-721  Piling.  The installation of all piling shall be subject to
controlled inspection. Such inspection shall be  performed  only  by  an
architect  or engineer resident at the site, except that where more than
one pile rig is working at  a  site,  inspection  of  the  work  may  be
performed  by  nonlicensed  or nonregistered personnel working under the
resident architect or engineer, who  need  act  only  in  a  supervisory
capacity.  This  exception  shall  not  apply,  however, in the cases of
timber or steel piles driven to end bearing as described in article  ten
of  this subchapter. Materials for piling shall be subject to inspection
requirements as prescribed in subchapter ten of this chapter  for  those
or  like  materials.  In  all  cases,  an inspector shall be assigned to
observe the operations of each rig.

Section 27-722

Section 27-722

  §  27-722  Footings, foundation piers, foundation walls and pile caps.
The provisions of section 27-683 of article six of this subchapter shall
apply.

Section 27-723

Section 27-723

  §  27-723  Subgrade  for  footings,  foundation  piers, and foundation
walls.   The soil  material  directly  underlying  footings,  foundation
piers,  and  foundation  walls  shall  be  inspected  by an architect or
engineer after excavation and immediately prior to construction  of  the
footings.  If  such inspection indicates that the soil conditions do not
conform to those assumed for purposes of design  and  described  on  the
plans,  or  are  unsatisfactory  due  to  disturbance,  then  additional
excavation, reduction in allowable bearing pressure, or  other  remedial
measures shall be adopted, as required. A copy of a report or reports on
such  inspection  or inspections describing the conditions found and any
necessary modification of the design, and bearing the signature  of  the
architect  or  engineer  making the inspections, shall be filed with the
commissioner.  In  addition,  notification  shall  be  received  by  the
department  at  least  two  working  days  prior  to construction of the
footing, pier, or foundation walls,  that  the  subgrade  is  ready  for
inspection   unless  the  requirements  of  section  27-209  of  article
twenty-one of subchapter one of this chapter have been met.

Section 27-724

Section 27-724

  §  27-724  Construction  required  for  or  affecting  the  support of
adjacent properties or buildings.  Except  in  cases  where  a  proposed
excavation  will extend less than ten feet below the legally established
grade, all underpinning operations and the construction  and  excavation
of   temporary  or  permanent  cofferdams,  caissons,  braced  excavated
surfaces,  or  other  constructions  or  excavations  required  for   or
affecting  the  support  of  adjacent  properties  or buildings shall be
subject  to  controlled  inspection.  The   details   of   underpinning,
cofferdams,  caissons,  bracing, or other constructions required for the
support of adjacent properties or buildings shall be shown on the  plans
or prepared in the form of shop or detail drawings and shall be approved
by the architect or engineer who prepared the plans.